LIFTING PLAN
(As per Singapore Standard and WSH Guidelines)
1. General Information
- Project Name: [Insert Project Name]
- Location of Lift: [Site Address]
- Date & Time: [DD/MM/YYYY] | [Time]
- Lift Type: ☐ Ordinary Lift ☐ Critical Lift
- Prepared By: [Name & Designation]
- Reviewed By: [Name & Designation]
- Approved By: [Competent Person]
2. Load Details
- Description of Load: [E.g., Steel Beams, Machinery, Pipes]
- Weight of Load: [XX] kg / tonnes
- Dimensions (L × W × H): [XX] m × [XX] m × [XX] m
- Center of Gravity: [Position]
- Any Special Considerations: [E.g., Fragile, Off-center weight]
3. Lifting Equipment & Accessories
- Type of Crane Used: ☐ Mobile Crane ☐ Tower Crane ☐ Crawler Crane ☐ Other: ________
- Crane Make & Model: [E.g., Tadano ATF 220G-5]
- Crane Capacity: [XX] tonnes
- Boom Length & Radius: [XX] m / [XX] m
- Lifting Accessories:
- Sling Type: [Wire Rope / Chain / Synthetic]
- Sling Length & SWL: [XX] m / [XX] tonnes
- Shackles & SWL: [XX] tonnes
- Hooks, Spreader Bars, Other: [Specify]
- Equipment Inspection Date: [DD/MM/YYYY] (Ensure valid Lifting Gear Certification)
4. Lifting Methodology
- Step-by-Step Procedure:
- Site Preparation – Set up exclusion zone, inspect ground conditions
- Crane Setup – Position crane, check boom angle, secure outriggers
- Load Securing – Attach slings/shackles, balance load
- Lifting Process – Signal confirmation, slow and controlled lift
- Load Placement – Lower load safely, confirm stability before release
- Post-Lift Checks – Inspect equipment, return to safe position
5. Personnel Involved
6. Risk Assessment & Control Measures
7. Site Preparation & Environmental Considerations
- Weather Check: ☐ Clear ☐ Rain ☐ Windy ☐ Other: _______
- Ground Stability Check: ☐ Stable ☐ Requires reinforcement
- Exclusion Zone Set: ☐ Yes ☐ No
- Barricades & Signage: ☐ Installed ☐ Not Required
- Permit to Work (PTW) Required: ☐ Yes ☐ No
8. Communication Plan
- Method: ☐ Hand Signals ☐ Radio ☐ Verbal Commands
- Responsible Person for Coordination: [Name]
9. Approval & Signatures
This Lifting Plan complies with Singapore’s WSH Act, SS 559:2010 (Code of Practice for Safe Lifting), and MOM Guidelines on Safe Lifting Operations.